Media
EN
May, 2023.

November, 2022.

October, 2022.

September, 2022.

September, 2022.

August, 2022.

Installation of all pipelines is under way in the EW Building

July, 2022.

Mining operations

July, 2022.

Upgrade of a stadium in Novaya Chara

June, 2022.

Piping and arrangement of process areas and fencing in the Grinding Buildings

May, 2022.

Trestle is handed over for the ore conveyor installation

April, 2022.

Construction of a new dormitory for the camp

April, 2022.

Installation and equipping of thickeners is in progress

March, 2022.

Structural steel erection for the Process Plant frame

March, 2022.

Arrangement of galleries of the Crushing and Conveying Complex

March, 2022.

Preparation works at the construction site at the transportation and storage area of the Railway Base of Udokan Copper in the vicinity of Novaya Chara station (BAM)

February, 2022.

Installation and equipping of thickeners is in progress at the Process Plant

January, 2022.

Civil works

December, 2021.

Installation of pipelines and process equipment in the HMP Buildings

November, 2021.

Civil works at the Coarse Ore Storage

October, 2021.

Improvements in Novaya Chara. Laying out a multi-functional public garden

October, 2021.

A new infectious diseases hospital building opened in Chara village. Engineering and construction of the facility were fully undertaken by the shareholders of Udokan Copper

September, 2021.

Completion of Bluzhdayuschy substation construction required for the operation of the smelter

September, 2021.

Structural steel erection at the above-ground part of the Coarse Ore Storage

August, 2021.

Construction of the Crushing and Conveying Complex

July, 2021.

Installation of stage 1 bulk flotation cells

July, 2021.

Installation of overhead cranes at the HMP Area

June, 2021.

Construction of the future Thickening and CCD Area

May, 2021.

Pilot Plant upgrade

May, 2021.

Visit of the Deputy Prime Minister and Presidential Plenipotentiary Envoy to the Far Eastern Federal District Yury Trutnev to Udokan

May, 2021.

Installation of a hoist at the Grinding Area

May, 2021.

Installation of the Gyratory Crusher

April, 2021.

Plant view from the observation site

April, 2021.

Completion of grinding mills assembly

March, 2021.

March, 2021.

Commencement of conveyor construction

February, 2021.

Construction of the last 23rd power transmission line pole

February, 2021.

Commencement of structural steel erection in the EW Building

January, 2021.

Equipment installation in the Grinding Building

December, 2020.

Structural steel erection

November, 2020.

Equipment installation at Bluzhdayuschy substation

November, 2020.

Concentrator view

October, 2020.

Mounting of sandwich panels in the Concentrator buildings

September, 2020.

Construction of Bluzhdayuschy substation

September, 2020.

Assembly of the Ball Mill shell

August, 2020.

Commencement of capital mining operations

August, 2020.

Mounting of panels in the Concentrator buildings

August, 2020.

Delivery of a transformer for Bluzhdayuschy substation

July, 2020.

Construction of the main motor road

June, 2020.

Construction of a power transmission line

June, 2020.

Construction of the Flotation Building

May, 2020.

Construction of a bridge across the Nirungnakan River

April, 2020.

Construction of Materials and Supply Base

March, 2020.

Installation of a pillar crane

February, 2020.

Installation of columns in the Reagent Preparation Building

January, 2020.

Structural steel erection

December, 2019.

First columns in the Reagent Preparation Building

November, 2019.

Foundation arrangement

October, 2019.

Transformer installation

October, 2019.

Transportation of a transformer for Udokan substation

September, 0019.

Foundation arrangement

September, 2019.

Construction of a conveyor dam

August, 2019.

60th power transmission line pole

August, 2019.

Operational exploration

July, 2019.

Concrete bedding. Bluzhdayuschy

June, 2019.

Grading for Udokan MMP

May, 2019.

Construction of the main motor road

May, 2019.

Construction of Udokan MMP substation

April, 2019.

Trip of the Governor of Zabaikalye Region to Udokan

March, 2019.

Installation of the first power transmission line pole

January, 2019.

Site grading

September, 2018.

Commencement of Udokan MMP construction. Groundbreaking